AI data centers in Indiana
3 large AI data centers in Indiana are tracked by Epoch AI, in New Carlisle, Jeffersonville, Fort Wayne. Together they are planned to draw 3.0 GW of IT power, 9% of all tracked US AI capacity (rank 3 of 18 states with a page).
- 3 sites
- 1.2 GW online today
- 3.0 GW planned
- #3 US state by planned power
fully online partly online (solid area = share running today) under construction
The sites
| Data center | Location | Owner | Main users | Online now (MW) | Planned (MW) | Full power by |
|---|---|---|---|---|---|---|
| Anthropic-Amazon New Carlisle | New Carlisle | Amazon | Anthropic | 1,037 | 1,925 | 2028-03 |
| Buildings 17-18 are operational. Next (2028-03): Buildings 19-32 are operational. | ||||||
| Google Fort Wayne | Fort Wayne | Google DeepMind | 0 | 863 | 2028-06 | |
| Building 2 has all cooling towers installed and is likely undergoing fit-out and commissioning. Next (2026-12): Estimated operational date of Building 2. | ||||||
| Meta Jeffersonville | Jeffersonville | Meta | Meta | 178 | 178 | online |
| Building 1 and 2 are operational. | ||||||
Grey rows: Epoch's latest construction note for each site, from satellite images, permits and filings.
Power coming online in Indiana
By the end of 2027 the tracked Indiana sites should reach about 1.73 GW of IT power. Hollow bars are planned dates.
online planned completion dates
Who builds and who uses them
Owners (by planned power): Amazon (1.9 GW), Google (863 MW), Meta (178 MW).
AI companies running on these sites: Anthropic, Meta, Google DeepMind.
Local opposition and moratoria in Indiana
| Where | Action | Status | Date | What it does | Sources |
|---|---|---|---|---|---|
| Elkhart | moratorium | in force | 2026-08-27 ends 2027-12-31 | The City Council suspended new applications for data centers and battery storage facilities through the end of 2027. | WNDU |
| Indianapolis (Marion County) | moratorium | in force | 2026-08-19 ends 2027-12-31 | The City-County Council voted 23-1 for a pause on new data centers, and the Metropolitan Development Commission gave final approval 6-0. It runs through 2027, and three projects already approved are exempt. | Mirror Indy |
| Fulton County | moratorium | in force | 2026-03-02 ends 2027-03-02 | Commissioners voted 2-1 for a one-year moratorium on data center construction, effective immediately, and set up a committee to study the effects. | WNDU |
Full list: data center moratorium tracker.
See all states on the US AI data center map.
Source and license
This page is built on free public data from Epoch AI, a nonprofit research institute that tracks AI compute, chips and data centers. Epoch AI publishes its data under the Creative Commons Attribution 4.0 license (CC BY 4.0), which allows reuse with credit.
- Epoch AI, ‘AI data centers’. Published online at epoch.ai. Retrieved from ‘https://epoch.ai/data/ai-data-centers’ [online resource]. Retrieved 2026-11-27.
What we changed: we kept the US sites only; placed each site on the map from its street address (US Census geocoder), ZIP code centre or the town named in Epoch's sources, so positions are approximate; removed confidence tags from owner and user names; took planned power and dates from Epoch's construction timelines; and summed totals by state and company. State outlines: US Census Bureau (public domain), via the us-atlas project (ISC license).
Reuse: you may reuse this page’s charts, maps, tables, text and calculations, including for commercial use, under the CC BY 4.0 license. Credit both sources, for example: “Source: Superintelligence Index (thesuperintelligenceindex.com), based on Epoch AI data, CC BY 4.0”, and link to this page. Epoch AI’s underlying data stays under its own CC BY 4.0 license. Our terms of use do not restrict either.
Epoch AI provides its data as-is and without warranties; see sections 5 and 6 of the license (disclaimer of warranties and limitation of liability). Epoch AI is not affiliated with this site and does not endorse it or our calculations. Any errors in the adaptation are ours. Information only, not financial advice.
Map outline license (us-atlas)
State outlines are drawn from us-atlas v3 (states-10m), derived from US Census Bureau cartographic boundary files (public domain).
Copyright 2013-2019 Michael Bostock. Permission to use, copy, modify, and/or distribute this software for any purpose with or without fee is hereby granted, provided that the above copyright notice and this permission notice appear in all copies. THE SOFTWARE IS PROVIDED “AS IS” AND THE AUTHOR DISCLAIMS ALL WARRANTIES WITH REGARD TO THIS SOFTWARE INCLUDING ALL IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS. IN NO EVENT SHALL THE AUTHOR BE LIABLE FOR ANY SPECIAL, DIRECT, INDIRECT, OR CONSEQUENTIAL DAMAGES OR ANY DAMAGES WHATSOEVER RESULTING FROM LOSS OF USE, DATA OR PROFITS, WHETHER IN AN ACTION OF CONTRACT, NEGLIGENCE OR OTHER TORTIOUS ACTION, ARISING OUT OF OR IN CONNECTION WITH THE USE OR PERFORMANCE OF THIS SOFTWARE.
Frequently asked questions
- How many AI data centers are in Indiana?
- Epoch AI tracks 3 large AI data centers in Indiana. Smaller and older data centers are not in the list.
- What is the largest AI data center in Indiana?
- Anthropic-Amazon New Carlisle in New Carlisle, owned by Amazon, planned at 1.9 GW of IT power by Epoch's estimate.
- How much power do AI data centers in Indiana use?
- About 1.2 GW of IT power today across the tracked sites, rising to 3.0 GW when all are built.
- Which companies are building AI data centers in Indiana?
- By planned power: Amazon, Google, Meta.
- Are there data center moratoriums in Indiana?
- Our tracker lists 3 local or state action(s) in Indiana; see the table on this page, each with sources.