Data center moratorium tracker
Towns, counties and states that have paused, banned or restricted new data centers as AI campuses ask for more power, water and land. Almost all came in 2025 and 2026. 79 actions in 33 states, each with its sources.
- 57 in force now
- 79 actions tracked
- 33 states
- Compiled 2026-11-27
In force now (57)
| Where | Action | Status | Date | What it does | Sources |
|---|---|---|---|---|---|
| Alpena Township, Michigan | moratorium | in force | 2026-11-23 ends 2027-11-23 | The township board adopted a one-year moratorium on accepting data center applications while it updates its zoning rules. | The Alpena News |
| Loudoun County, Virginia | pause | in force | 2026-11-17 | The Board of Supervisors voted 7-1 to pause new legislative applications for data centers and substations. Reasons cited were grid capacity, infrastructure, noise and air quality. Reports give the length as 10 months; the county describes it as up to 12 months. | FOX 5 DC |
| San Jose, California | moratorium | in force | 2026-11-17 | The City Council unanimously paused land-use approvals for data centers and other large energy users, including 12 pending projects, until new standards take effect. | San José Spotlight |
| Rochester, Minnesota | moratorium | in force | 2026-11-16 | The City Council voted 5-1 to adopt a data center moratorium, joining several other Minnesota cities. | Post Bulletin |
| Hudson, Massachusetts | moratorium | in force | 2026-11-16 ends 2027-12-31 | Town meeting voters approved a moratorium on data centers through the end of 2027. | MetroWest Daily News via Yahoo News |
| Boise, Idaho | moratorium | in force | 2026-11-10 | The City Council unanimously passed an emergency moratorium on large data centers, effective immediately. | CBS2 Idaho News |
| Dade County, Georgia | moratorium | in force | 2026-11-05 ends 2027-02-03 | Commissioners unanimously approved a 90-day moratorium after residents objected to a proposed 300-megawatt data center. The end date is 90 days after adoption. | Chattanooga Times Free Press |
| Guilford County, North Carolina | moratorium | in force | 2026-11-05 ends 2028-05-05 | Commissioners unanimously adopted an 18-month moratorium on data centers in unincorporated areas. There were no pending applications. | Rhino Times |
| Trenton, Ohio | zoning ban | in force | 2026-11-03 | Voters approved Issue 17, a city charter amendment that permanently bans large data centers in Trenton. | WVXU |
| North Berwick, Maine | zoning ban | in force | 2026-11-03 | Town voters approved a permanent ban on data centers, with about 78% in favor. It was one of at least eight Maine towns that voted to restrict data centers that day. | Bangor Daily News |
| Wells, Maine | moratorium | in force | 2026-11-03 | Town voters approved a 180-day moratorium on data centers. Peru, Eliot, Brownfield, Freedom, Sabattus and Wiscasset approved similar 180-day bans the same day. | Bangor Daily News |
| St. Johns County, Florida | moratorium | in force | 2026-11-03 ends 2027-10-31 | Commissioners approved a one-year moratorium on medium and large data centers, expiring October 31, 2027. | Jacksonville Today |
| Clinton Township (Macomb County), Michigan | moratorium | in force | 2026-11 | Trustees approved a 180-day moratorium on building data centers so the township can write local rules. It has no data centers today. Press reported the vote on November 3, 2026; the exact adoption date was not confirmed. | C & G Newspapers |
| McHenry County, Illinois | moratorium | in force | 2026-11 | The County Board approved a 12-month moratorium on data centers. | Northwest Herald (Shaw Local) |
| Manatee County, Florida | moratorium | in force | 2026-10-08 | County commissioners approved a 12-month moratorium on new data center applications in unincorporated areas. | Manatee County Government |
| San Francisco, California | moratorium | in force | 2026-10-06 | The city adopted a 45-day zoning moratorium on data centers. On November 17 supervisors voted unanimously to extend it to September 2027; the extension takes effect unless the mayor vetoes it within about ten days, which was not confirmed here. | The San Francisco Standard |
| Mesa County, Colorado | moratorium | in force | 2026-09-30 ends 2027-09-30 | Commissioners unanimously approved a one-year moratorium on land-use applications for data centers in unincorporated areas. | KJCT |
| Pima County, Arizona | moratorium | in force | 2026-09-23 ends 2027-01-21 | Supervisors voted 3-2 for a 120-day moratorium on new data centers while the county writes zoning rules for them. It does not affect the already approved Project Blue. The end date is 120 days after adoption. | Arizona Luminaria |
| Marshall County, Iowa | moratorium | in force | 2026-09-23 ends 2027-03-23 | Supervisors voted 3-0 for a six-month data center moratorium. The end date is six months after adoption. | Times-Republican |
| Salem, Oregon | moratorium | in force | 2026-09-21 ends 2027-01-19 | The City Council gave final approval to a 120-day moratorium on new data centers while a task force studies rules, and may consider extending it in January. The end date is 120 days after adoption. | KATU |
| Spartanburg County, South Carolina | moratorium | in force | 2026-09-21 | County Council passed, on third reading and with amendments, a one-year moratorium on data centers. Reasons cited were grid, water and air quality. | FOX Carolina |
| Woodford County, Kentucky | zoning ban | in force | 2026-09-08 | The Fiscal Court passed a permanent ban on data centers, landfills and large battery storage facilities. It is reported as the first permanent county ban on data centers in Kentucky. | WUKY / Kentucky Lantern |
| Lake County, Illinois | moratorium | in force | 2026-09-08 | The County Board approved an eight-month moratorium on data centers in unincorporated areas after receiving more than 1,200 public comments. Eight months from adoption ends around May 2027. | Lake County, Illinois |
| Miamisburg, Ohio | moratorium | in force | 2026-09-01 ends 2027-06-01 | The City Council voted 6-0 for a nine-month moratorium on data centers, prompted by interest in a data center at a former power station site. The end date is nine months after adoption. | City of Miamisburg |
| Elkhart, Indiana | moratorium | in force | 2026-08-27 ends 2027-12-31 | The City Council suspended new applications for data centers and battery storage facilities through the end of 2027. | WNDU |
| Durham County, North Carolina | moratorium | in force | 2026-08-24 | Commissioners voted 4-1 for a nine-month moratorium on large-scale data centers, running until May 2027. | WUNC |
| Indianapolis (Marion County), Indiana | moratorium | in force | 2026-08-19 ends 2027-12-31 | The City-County Council voted 23-1 for a pause on new data centers, and the Metropolitan Development Commission gave final approval 6-0. It runs through 2027, and three projects already approved are exempt. | Mirror Indy |
| Shawnee County, Kansas | moratorium | in force | 2026-08-13 | Commissioners approved a six-month moratorium on new data center applications, set to expire in February 2027. | KSNT |
| Hillsboro, Oregon | moratorium | extended | 2026-07-27 | The City Council unanimously adopted a 120-day moratorium on new or expanded data centers and battery storage. In November 2026 it extended the moratorium by six months, to around May 2027. | Hillsboro News-Times Forest Grove News-Times |
| Nodaway County, Missouri | moratorium | in force | 2026-07-21 ends 2027-01-21 | Commissioners unanimously approved a six-month moratorium on building data centers and their supporting facilities while questions about a proposed project are answered. The end date is six months after adoption. | KXCV-KRNW |
| Greenwood County, South Carolina | moratorium | in force | 2026-07-21 | County Council approved on final reading a one-year moratorium on data centers. | FOX Carolina |
| Nashville-Davidson County, Tennessee | moratorium | in force | 2026-07-21 ends 2026-12-01 | The Metro Council passed a moratorium on data center permits until December 1, 2026, together with new zoning rules that bar the largest hyperscale tier. One developer has challenged the rules in federal court. | Nashville Banner |
| Cleveland, Ohio | moratorium | extended | 2026-07-15 ends 2027-01-29 | The City Council voted 14-1 for a three-month moratorium on data centers while a working group drafts recommendations. In October it extended the moratorium to January 29, 2027. | Cleveland 19 News Baxtel |
| State of New York (Executive Order 62) | moratorium | in force | 2026-07-14 | The governor ordered the state environmental agency to hold pending discretionary permits for new or expanded data centers of 50 megawatts or more until a statewide environmental impact study is finished. It cites grid strain, ratepayer costs, water, air and noise, and does not cover local permits. | Office of the Governor of New York |
| Sarasota County, Florida | moratorium | in force | 2026-07-08 | The county halted applications for hyperscale data centers until at least July 2027. Neighboring DeSoto County had taken a similar step earlier. | WGCU |
| Prince George's County, Maryland | moratorium | extended | 2026-07-07 | The County Council passed a two-year moratorium on hyperscale data center development, extending an earlier pause. | WTOP |
| Paulding County, Georgia | moratorium | in force | 2026-07 ends 2027-01-01 | Commissioners unanimously froze new data center projects until January 1, 2027, while the county updates its development codes. | FOX 5 Atlanta |
| Town of Brookhaven, New York | moratorium | in force | 2026-07 | After a long public hearing, the town board approved an 18-month moratorium on approving new data centers, citing the electric grid and protection of the drinking-water aquifer. | Fire Island News |
| Montgomery County, Maryland | moratorium | in force | 2026-07 | The County Council approved an 18-month moratorium on permits for large data centers, along with a zoning change that bars hyperscale data centers for now. It followed a six-month executive order issued in June. | Montgomery County Government |
| Town of East Fishkill, New York | moratorium | in force | 2026-06-25 | The town board unanimously adopted a three-year moratorium on data centers over 20 megawatts, running to July 2029. It was prompted by a proposed campus of about 1,000 megawatts. | WAMC |
| Box Elder County, Utah | moratorium | in force | 2026-06-17 ends 2026-12-14 | Commissioners unanimously passed a 180-day moratorium on new data centers and their power plants in unincorporated areas. It does not affect the already proposed Stratos project. The end date is 180 days after adoption. | Utah Public Radio |
| San Marcos, Texas | zoning ban | in force | 2026-06-16 | The City Council voted 4-3 to make data centers ineligible in every zoning district, using its home-rule zoning powers. It became the first Texas city to do so. A state senator has said he will challenge the ban. | The Texas Tribune |
| Butler County, Ohio | moratorium | in force | 2026-06-16 ends 2026-12-16 | Commissioners unanimously approved a six-month moratorium on data centers in the six townships under county zoning: Hanover, Lemon, Madison, Milford, Oxford and Ross. The end date is six months after adoption. | WVXU |
| Lexington-Fayette Urban County, Kentucky | moratorium | extended | 2026-06-09 ends 2027-10-31 | The council unanimously paused permits, development plans and zone changes for data centers. In October 2026 it extended the pause to October 31, 2027. | Lexington-Fayette Urban County Government |
| Dane County, Wisconsin | moratorium | in force | 2026-06-04 | The County Board unanimously paused zoning permit applications for hyperscale data centers until December 2027. It covers the 26 towns under county zoning and was modeled on Manitowoc County's rule. | Isthmus |
| Charlotte, North Carolina | moratorium | extended | 2026-06 ends 2027-10-18 | The city adopted a 150-day moratorium on data centers in June 2026. On October 26 the City Council voted unanimously to extend it to October 18, 2027. | WFAE |
| Denver, Colorado | moratorium | in force | 2026-05-18 ends 2027-05-18 | The City Council unanimously paused approvals of new data centers for one year. | Mile High CRE |
| Northampton County, North Carolina | moratorium | in force | 2026-05 | The county adopted a 32-month moratorium on data centers in May 2026, according to regional public radio reporting. | WFDD |
| Muncy Township (Lycoming County), Pennsylvania | moratorium | in force | 2026-05 | The township passed a nine-month moratorium on data centers and similar high-intensity data processing uses, ending earlier if a zoning ordinance regulating them is adopted first. It was reported on May 1, 2026; the exact vote date was not confirmed. | Williamsport Sun-Gazette |
| Manitowoc County, Wisconsin | moratorium | in force | 2026-04 | The County Board unanimously approved an 18-month moratorium on accepting data center applications and issuing permits. Three towns had asked for it, which puts the end around late 2027. | Wisconsin Public Radio |
| Oklahoma City, Oklahoma | moratorium | extended | 2026-04 ends 2027-12-31 | The city enacted a data center moratorium in April 2026 that was set to run through December. On November 10 the City Council voted unanimously to extend it through 2027, with two properties already in rezoning exempt. | The Oklahoman via Yahoo News |
| Fulton County, Indiana | moratorium | in force | 2026-03-02 ends 2027-03-02 | Commissioners voted 2-1 for a one-year moratorium on data center construction, effective immediately, and set up a committee to study the effects. | WNDU |
| Royalton, Vermont | moratorium | in force | 2026-03 | Town voters approved a five-year municipal moratorium on AI and cryptocurrency data centers. None exist or are proposed in the town. | Compass Vermont |
| Big Rapids Charter Township (Mecosta County), Michigan | moratorium | in force | 2026-02-23 ends 2027-02-23 | The township adopted an ordinance placing a one-year moratorium on permitting, review and construction of data centers. It cites water use, energy use and noise, and allows extensions by resolution. | Big Rapids Charter Township |
| Eagan, Minnesota | pause | in force | 2026-02-17 | The City Council approved a pause of up to one year on data centers larger than 20 megawatts or within 500 feet of homes, citing water and electricity demand. | KSTP |
| Baltimore County, Maryland | moratorium | extended | 2026-02-02 | The County Council passed a temporary freeze on data center development pending a study, originally capped at January 1, 2027. In September 2026 it voted unanimously to extend the freeze. | The Baltimore Banner WYPR |
| Larimer County, Colorado | moratorium | extended | 2026-01-27 ends 2027-02-25 | The county paused new land-use applications for data centers in unincorporated areas, citing water, power, noise and the lack of code definitions. It has been extended twice, most recently to February 25, 2027. | Larimer County |
Ended, failed, pending or unclear (22)
Bills not yet signed, votes against single projects, court rulings, and pauses that expired, were lifted or whose renewal we could not confirm.
| Where | Action | Status | Date | What it does | Sources |
|---|---|---|---|---|---|
| Boulder County, Colorado | moratorium | lifted | 2026-11 | Commissioners approved new data center rules in the county code, which ended the county's earlier data center moratorium. The date shown is when the rules were adopted; the moratorium's original start date was not confirmed. | KDVR via Yahoo News |
| State of Texas (governor's directives) | other | in force | 2026-08-03 | Gov. Abbott froze new data center projects pending a state audit, and the grid operator ERCOT paused part of its review of large new loads. In September he also told the state environmental agency, TCEQ, to stop issuing new permits for data centers. No end date has been set. | The Texas Tribune The Texas Tribune |
| Minneapolis, Minnesota | pause | unclear | 2026-06-25 ends 2026-11-25 | The City Council approved a five-month pause on new data centers, exempting smaller downtown facilities under 350,000 square feet. Five months from adoption ends around November 25, 2026, and no extension was confirmed. | CBS News Minnesota |
| Jackson County, Missouri | moratorium | unclear | 2026-06-22 | The County Legislature passed a 180-day pause on applications for data centers and battery storage and sent it to the County Executive, who said he supports it. His signature was not confirmed. | KCTV5 |
| Seattle, Washington | moratorium | unclear | 2026-06-09 | The City Council unanimously passed a one-year emergency moratorium on new large data centers, citing grid capacity, water and electricity rates. It takes effect once the mayor signs it, which was not confirmed here. | GeekWire |
| State of New York (S10642 / A11560) | state bill | passed | 2026-06-04 | The legislature passed a bill that would impose a one-year moratorium on new state environmental permits for large data centers, along with cost-allocation rules. The Senate vote was 43-17. As of compilation it had not been delivered to or signed by the governor. | New York State Senate |
| DeKalb County, Georgia | moratorium | unclear | 2026-06 ends 2026-09-30 | Commissioners extended an existing moratorium on new data center applications by about 100 days, to the end of September 2026. It had been due to expire on June 23. No later action was confirmed, so its current status is unclear. | CBS News Atlanta |
| Imperial County, California | moratorium | lifted | 2026-06 | The county adopted a 45-day data center moratorium and in July extended it by about ten and a half months. The Superior Court then ordered it set aside because the county's findings were insufficient. | County of Imperial |
| Logan County, Illinois | moratorium | unclear | 2026-05-19 | The County Board voted 6-4 for a 12-month data center moratorium. In June the State's Attorney declared it invalid for procedural defects. No court ruling or re-adoption was found, so its status is unclear. | Illinois Times |
| Hill County, Texas | moratorium | lifted | 2026-05 | This appears to have been the first Texas county moratorium on data centers, a pause of up to one year. About two weeks later, after a developer sued for $100 million, commissioners unanimously rescinded it and adopted a checklist of developer requirements instead. | The Texas Tribune |
| State of Vermont (H.727) | state bill | failed | 2026-05 | Gov. Scott vetoed H.727, a bill to regulate data center development (not a moratorium), and the House sustained the veto 83-52. A separate bill for a moratorium on data centers over 100 megawatts until 2030 did not advance. | Compass Vermont Vermont Natural Resources Council |
| State of Maine (LD 307) | state bill | failed | 2026-04-24 | The legislature passed a temporary statewide moratorium on large data centers over 20 megawatts. Gov. Mills vetoed it because it lacked an exemption for a planned project in Jay. On April 29 the House vote to override fell short of two-thirds. | Office of the Governor of Maine Spectrum News Maine |
| Birmingham, Alabama | moratorium | expired | 2026-03-03 | The city adopted a 180-day moratorium on data centers in March 2026. In June the City Council replaced it with a data center ordinance setting rules for future projects. | Alabama Political Reporter |
| State of South Dakota (SB 232) | state bill | failed | 2026-02-18 | A bill for a one-year statewide moratorium on hyperscale data center construction stalled in committee and did not advance. | Data Center Record |
| Hood County, Texas | moratorium | failed | 2026-02 | Commissioners twice considered a data center moratorium and did not pass it, after a state lawmaker warned that Texas counties lack the authority to impose one. | The Texas Tribune |
| Jerome Township (Union County), Ohio | moratorium | unclear | 2025-09-03 | Trustees unanimously adopted a nine-month moratorium on new data center construction while they revisit zoning. The term ended around June 2026, and no renewal or replacement was confirmed. | WYSU / WOSU |
| Prince William County (PW Digital Gateway), Virginia | other | in force | 2025-08-07 | A circuit judge voided the county's rezoning for the large Digital Gateway data center corridor because hearing notices were improper. The ruling was upheld on appeal, and in July 2026 the developer QTS dropped its appeal, so those approvals no longer stand. | Potomac Local FOX 5 DC |
| Tucson, Arizona | other | passed | 2025-08-06 | The City Council voted 7-0 to stop negotiating over the Project Blue data center and to drop the planned annexation of its site, after public concern about water use. | Arizona Luminaria KOLD |
| St. Charles, Missouri | moratorium | unclear | 2025-08 | All ten council members voted for a one-year moratorium on applications for new or expanded data centers. The term ended around August 2026, and no renewal was confirmed. | Spectrum News |
| Oldham County, Kentucky | moratorium | expired | 2025-07-01 ends 2025-11-28 | The Fiscal Court voted 4-2 for a 150-day hold on data center applications, with no waivers, while a large proposal drew local opposition. The end date is 150 days after adoption. | Louisville Public Media |
| Coweta County, Georgia | moratorium | unclear | 2025-05 | Commissioners unanimously adopted a 180-day moratorium in May 2025, after the $17 billion Project Sail campus was proposed, and it ran until November 2025. Local press reported a second 180-day pause on 2026-06-16, running to about late December 2026, but that report could not be fetched to confirm, so the current status is unclear. | GovTech (Atlanta Journal-Constitution) WSB-TV via Yahoo News The Newnan Times-Herald |
| Douglas County, Georgia | moratorium | expired | 2025-03 | The county adopted a 90-day moratorium on data centers in March 2025, the first in the Atlanta area, so it could review its rules. A 90-day term would have ended around June 2025. | GovTech (Atlanta Journal-Constitution) |
Status as of the compile date; temporary moratoria often get extended or replaced by new zoning rules, so check the sources. Types: moratorium 65, zoning ban 4, state bill 4, pause 3, other 3. Candidates came from news searches and the Data Center Census tracker. Each entry was checked against at least one fetched primary or news source, and its status was worked out as of 2026-11-27 from the adoption date and the stated length.
By state
Georgia (5), Ohio (5), Texas (4), New York (4), North Carolina (4), Colorado (4), Indiana (3), Michigan (3), Minnesota (3), Missouri (3), Maine (3), Maryland (3), California (3), Kentucky (3), Illinois (3), Florida (3), Virginia (2), Arizona (2), Wisconsin (2), Oregon (2), Vermont (2), South Carolina (2), Oklahoma (1), Washington (1), Tennessee (1), Idaho (1), Utah (1), Kansas (1), Iowa (1), Massachusetts (1), Alabama (1), Pennsylvania (1), South Dakota (1).
Why places pause data centers
The reasons in these actions repeat: strain on the power grid and fear of higher electricity bills, water use for cooling, noise from cooling equipment and backup generators, loss of farmland, and tax deals that bring few jobs. A moratorium usually gives a town time to write zoning rules for data centers, then ends.
Where the tracked AI data centers are: US AI data center map.
Frequently asked questions
- What is a data center moratorium?
- A temporary pause, set by a town, county or state, on accepting or approving new data center projects, usually while it writes zoning rules for them.
- Which states have data center moratoriums?
- Our tracker lists 57 moratoriums or bans in force and 79 actions in all, in 33 states, most in Georgia, Ohio, Texas, New York.
- Why are communities opposing data centers?
- Mainly power grid strain and electricity prices, water use, noise, farmland loss and tax incentives.