AI data centers in Oregon

2 large AI data centers in Oregon are tracked by Epoch AI, in The Dalles, Hillsboro. Together they are planned to draw 334 MW of IT power, 1% of all tracked US AI capacity (rank 17 of 18 states with a page).

OregonMeta-QTS Hillsboro 2 — Hillsboro, Oregon. Owner Meta; users Meta. 180 MW online now. Epoch AI estimate.Google The Dalles — The Dalles, Oregon. Owner Google; users unknown. 154 MW online now. Epoch AI estimate.Hillsboro 180 MWThe Dalles 154 MW
Circle area = planned IT power. Locations approximate.

fully online partly online (solid area = share running today) under construction

The sites

Data centerLocationOwnerMain usersOnline now (MW)Planned (MW)Full power by
Meta-QTS Hillsboro 2HillsboroMetaMeta180180online
All four buildings are operational.
Google The DallesThe DallesGoogle–154154online
Building 2 is estimated to be operational, based on all external equipment being installed, and ordinary cars parked by the building.

Grey rows: Epoch's latest construction note for each site, from satellite images, permits and filings.

Source: Epoch AI, ‘AI data centers’, licensed under CC BY 4.0; adapted by us (see Source and license below). Retrieved 2026-11-27.Estimates; locations approximate

Power coming online in Oregon

By the end of 2027 the tracked Oregon sites should reach about 0.33 GW of IT power. Hollow bars are planned dates.

0 GW0.1 GW0.2 GW0.3 GW202320242025202620272028End 2023: 0.04 GW IT powerEnd 2024: 0.18 GW IT powerEnd 2025: 0.26 GW IT powerToday: 0.33 GW IT powerEnd 2027: 0.33 GW IT powerEnd 2028: 0.33 GW IT power

online planned completion dates

Who builds and who uses them

Owners (by planned power): Meta (180 MW), Google (154 MW).
AI companies running on these sites: Meta.

Local opposition and moratoria in Oregon

WhereActionStatusDateWhat it doesSources
Salemmoratoriumin force2026-09-21
ends 2027-01-19
The City Council gave final approval to a 120-day moratorium on new data centers while a task force studies rules, and may consider extending it in January. The end date is 120 days after adoption.KATU
Hillsboromoratoriumextended2026-07-27The City Council unanimously adopted a 120-day moratorium on new or expanded data centers and battery storage. In November 2026 it extended the moratorium by six months, to around May 2027.Hillsboro News-Times Forest Grove News-Times

Full list: data center moratorium tracker.

See all states on the US AI data center map.

Source and license

This page is built on free public data from Epoch AI, a nonprofit research institute that tracks AI compute, chips and data centers. Epoch AI publishes its data under the Creative Commons Attribution 4.0 license (CC BY 4.0), which allows reuse with credit.

What we changed: we kept the US sites only; placed each site on the map from its street address (US Census geocoder), ZIP code centre or the town named in Epoch's sources, so positions are approximate; removed confidence tags from owner and user names; took planned power and dates from Epoch's construction timelines; and summed totals by state and company. State outlines: US Census Bureau (public domain), via the us-atlas project (ISC license).

Reuse: you may reuse this page’s charts, maps, tables, text and calculations, including for commercial use, under the CC BY 4.0 license. Credit both sources, for example: “Source: Superintelligence Index (thesuperintelligenceindex.com), based on Epoch AI data, CC BY 4.0”, and link to this page. Epoch AI’s underlying data stays under its own CC BY 4.0 license. Our terms of use do not restrict either.

Epoch AI provides its data as-is and without warranties; see sections 5 and 6 of the license (disclaimer of warranties and limitation of liability). Epoch AI is not affiliated with this site and does not endorse it or our calculations. Any errors in the adaptation are ours. Information only, not financial advice.

Map outline license (us-atlas)

State outlines are drawn from us-atlas v3 (states-10m), derived from US Census Bureau cartographic boundary files (public domain).

Copyright 2013-2019 Michael Bostock. Permission to use, copy, modify, and/or distribute this software for any purpose with or without fee is hereby granted, provided that the above copyright notice and this permission notice appear in all copies. THE SOFTWARE IS PROVIDED “AS IS” AND THE AUTHOR DISCLAIMS ALL WARRANTIES WITH REGARD TO THIS SOFTWARE INCLUDING ALL IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS. IN NO EVENT SHALL THE AUTHOR BE LIABLE FOR ANY SPECIAL, DIRECT, INDIRECT, OR CONSEQUENTIAL DAMAGES OR ANY DAMAGES WHATSOEVER RESULTING FROM LOSS OF USE, DATA OR PROFITS, WHETHER IN AN ACTION OF CONTRACT, NEGLIGENCE OR OTHER TORTIOUS ACTION, ARISING OUT OF OR IN CONNECTION WITH THE USE OR PERFORMANCE OF THIS SOFTWARE.

Frequently asked questions

How many AI data centers are in Oregon?
Epoch AI tracks 2 large AI data centers in Oregon. Smaller and older data centers are not in the list.
What is the largest AI data center in Oregon?
Meta-QTS Hillsboro 2 in Hillsboro, owned by Meta, planned at 180 MW of IT power by Epoch's estimate.
How much power do AI data centers in Oregon use?
About 334 MW of IT power today across the tracked sites, rising to 334 MW when all are built.
Which companies are building AI data centers in Oregon?
By planned power: Meta, Google.
Are there data center moratoriums in Oregon?
Our tracker lists 2 local or state action(s) in Oregon; see the table on this page, each with sources.