AI data centers in Texas
14 large AI data centers in Texas are tracked by Epoch AI, in Abilene, San Antonio, Denton, Temple…. Together they are planned to draw 6.5 GW of IT power, 20% of all tracked US AI capacity (rank 1 of 18 states with a page).
- 14 sites
- 1.7 GW online today
- 6.5 GW planned
- #1 US state by planned power
fully online partly online (solid area = share running today) under construction
The sites
| Data center | Location | Owner | Main users | Online now (MW) | Planned (MW) | Full power by |
|---|---|---|---|---|---|---|
| OpenAI Stargate Shackelford | Abilene | Oracle | OpenAI | 0 | 1,400 | 2028-11 |
| Buildings 1-5 shells complete and fully roofed. Next (2027-08): Building 1 is operational (estimate). | ||||||
| Goodnight | Claude | Google DeepMind | 0 | 1,006 | 2027-10 | |
| Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. Next (2027-03): Building 1 operational. | ||||||
| OpenAI Stargate Milam | Milam County | Softbank | OpenAI | 0 | 857 | 2028-12 |
| Steel framing and roofing is underway for Building 1. Next (2028-12): All buildings finished, site is fully operational. | ||||||
| OpenAI Stargate Abilene | Abilene | Oracle | OpenAI | 824 | 824 | online |
| Buildings 7-8 are estimated to be operational. | ||||||
| Crusoe Abilene Expansion | Abilene | Microsoft | Microsoft | 0 | 672 | 2027-11 |
| Land clearing continues. Next (2027-09): Building 1 operational. | ||||||
| Coreweave Helios | Afton | CoreWeave | OpenAI | 132 | 528 | 2029-01 |
| Building 1 operational at full capacity. Next (2028-01): Building 2 and 3 are operational at full capacity. | ||||||
| CoreWeave Denton TX | Denton | CoreWeave | OpenAI | 262 | 282 | 2027-05 |
| Building 8 interior fit-out scheduled to begin. Next (2027-05): Building 8 projected operational. | ||||||
| Anthropic Barber Lake | Colorado City | Cipher Mining | Anthropic | 0 | 207 | 2027-04 |
| Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Next (2026-12): Building 1 Phase I is operational: 168 MW critical IT power (244 MW gross), running Google TPU v7 (chip type inferred, tagged likely). | ||||||
| Meta Temple | Temple | Meta | Meta | 178 | 178 | online |
| Building 3 is operational. | ||||||
| Google Red Oak | Red Oak | – | 77 | 154 | 2026-12 | |
| Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot. Next (2026-12): Building 2 is estimated to be operational. | ||||||
| Vantage TX1 | San Antonio | – | – | 32 | 128 | 2027-08 |
| Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Next (2027-08): Estimated construction completion date of Building 2. | ||||||
| Google Midlothian | Midlothian | – | 103 | 103 | online | |
| Estimated full completion of the expanded row of cooling towers and backup generators for Building 1. | ||||||
| Microsoft SAT40 | San Antonio | Microsoft | – | 75 | 75 | online |
| Site has already been completed, with no more visible construction on any building. | ||||||
| Microsoft SAT14 | San Antonio | Microsoft | – | 47 | 47 | online |
| Building 2 fully operational, Building 1 expanded. | ||||||
Grey rows: Epoch's latest construction note for each site, from satellite images, permits and filings.
Power coming online in Texas
By the end of 2027 the tracked Texas sites should reach about 4.23 GW of IT power. Hollow bars are planned dates.
online planned completion dates
Who builds and who uses them
Owners (by planned power): Oracle (2.2 GW), Google (1.3 GW), Softbank (857 MW), CoreWeave (810 MW), Microsoft (794 MW), Cipher Mining (207 MW).
AI companies running on these sites: OpenAI, Meta, Anthropic, Microsoft, Google DeepMind.
Local opposition and moratoria in Texas
| Where | Action | Status | Date | What it does | Sources |
|---|---|---|---|---|---|
| State of Texas (governor's directives) | other | in force | 2026-08-03 | Gov. Abbott froze new data center projects pending a state audit, and the grid operator ERCOT paused part of its review of large new loads. In September he also told the state environmental agency, TCEQ, to stop issuing new permits for data centers. No end date has been set. | The Texas Tribune The Texas Tribune |
| San Marcos | zoning ban | in force | 2026-06-16 | The City Council voted 4-3 to make data centers ineligible in every zoning district, using its home-rule zoning powers. It became the first Texas city to do so. A state senator has said he will challenge the ban. | The Texas Tribune |
| Hill County | moratorium | lifted | 2026-05 | This appears to have been the first Texas county moratorium on data centers, a pause of up to one year. About two weeks later, after a developer sued for $100 million, commissioners unanimously rescinded it and adopted a checklist of developer requirements instead. | The Texas Tribune |
| Hood County | moratorium | failed | 2026-02 | Commissioners twice considered a data center moratorium and did not pass it, after a state lawmaker warned that Texas counties lack the authority to impose one. | The Texas Tribune |
Full list: data center moratorium tracker.
See all states on the US AI data center map.
Source and license
This page is built on free public data from Epoch AI, a nonprofit research institute that tracks AI compute, chips and data centers. Epoch AI publishes its data under the Creative Commons Attribution 4.0 license (CC BY 4.0), which allows reuse with credit.
- Epoch AI, ‘AI data centers’. Published online at epoch.ai. Retrieved from ‘https://epoch.ai/data/ai-data-centers’ [online resource]. Retrieved 2026-11-27.
What we changed: we kept the US sites only; placed each site on the map from its street address (US Census geocoder), ZIP code centre or the town named in Epoch's sources, so positions are approximate; removed confidence tags from owner and user names; took planned power and dates from Epoch's construction timelines; and summed totals by state and company. State outlines: US Census Bureau (public domain), via the us-atlas project (ISC license).
Reuse: you may reuse this page’s charts, maps, tables, text and calculations, including for commercial use, under the CC BY 4.0 license. Credit both sources, for example: “Source: Superintelligence Index (thesuperintelligenceindex.com), based on Epoch AI data, CC BY 4.0”, and link to this page. Epoch AI’s underlying data stays under its own CC BY 4.0 license. Our terms of use do not restrict either.
Epoch AI provides its data as-is and without warranties; see sections 5 and 6 of the license (disclaimer of warranties and limitation of liability). Epoch AI is not affiliated with this site and does not endorse it or our calculations. Any errors in the adaptation are ours. Information only, not financial advice.
Map outline license (us-atlas)
State outlines are drawn from us-atlas v3 (states-10m), derived from US Census Bureau cartographic boundary files (public domain).
Copyright 2013-2019 Michael Bostock. Permission to use, copy, modify, and/or distribute this software for any purpose with or without fee is hereby granted, provided that the above copyright notice and this permission notice appear in all copies. THE SOFTWARE IS PROVIDED “AS IS” AND THE AUTHOR DISCLAIMS ALL WARRANTIES WITH REGARD TO THIS SOFTWARE INCLUDING ALL IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS. IN NO EVENT SHALL THE AUTHOR BE LIABLE FOR ANY SPECIAL, DIRECT, INDIRECT, OR CONSEQUENTIAL DAMAGES OR ANY DAMAGES WHATSOEVER RESULTING FROM LOSS OF USE, DATA OR PROFITS, WHETHER IN AN ACTION OF CONTRACT, NEGLIGENCE OR OTHER TORTIOUS ACTION, ARISING OUT OF OR IN CONNECTION WITH THE USE OR PERFORMANCE OF THIS SOFTWARE.
Frequently asked questions
- How many AI data centers are in Texas?
- Epoch AI tracks 14 large AI data centers in Texas. Smaller and older data centers are not in the list.
- What is the largest AI data center in Texas?
- OpenAI Stargate Shackelford in Abilene, owned by Oracle, planned at 1.4 GW of IT power by Epoch's estimate.
- How much power do AI data centers in Texas use?
- About 1.7 GW of IT power today across the tracked sites, rising to 6.5 GW when all are built.
- Which companies are building AI data centers in Texas?
- By planned power: Oracle, Google, Softbank, CoreWeave, Microsoft.
- Are there data center moratoriums in Texas?
- Our tracker lists 4 local or state action(s) in Texas; see the table on this page, each with sources.