AI data centers in Texas

14 large AI data centers in Texas are tracked by Epoch AI, in Abilene, San Antonio, Denton, Temple…. Together they are planned to draw 6.5 GW of IT power, 20% of all tracked US AI capacity (rank 1 of 18 states with a page).

TexasOpenAI Stargate Shackelford — Abilene, Texas. Owner Oracle; users OpenAI. 0 MW online now, 1,400 MW planned by 2028-11. Epoch AI estimate.Goodnight — Claude, Texas. Owner Google; users Google DeepMind. 0 MW online now, 1,006 MW planned by 2027-10. Epoch AI estimate.OpenAI Stargate Milam — Milam County, Texas. Owner Softbank; users OpenAI. 0 MW online now, 857 MW planned by 2028-12. Epoch AI estimate.OpenAI Stargate Abilene — Abilene, Texas. Owner Oracle; users OpenAI. 824 MW online now. Epoch AI estimate.Crusoe Abilene Expansion — Abilene, Texas. Owner Microsoft; users Microsoft. 0 MW online now, 672 MW planned by 2027-11. Epoch AI estimate.Coreweave Helios — Afton, Texas. Owner CoreWeave; users OpenAI. 132 MW online now, 528 MW planned by 2029-01. Epoch AI estimate.CoreWeave Denton TX — Denton, Texas. Owner CoreWeave; users OpenAI. 262 MW online now, 282 MW planned by 2027-05. Epoch AI estimate.Anthropic Barber Lake — Colorado City, Texas. Owner Cipher Mining; users Anthropic. 0 MW online now, 207 MW planned by 2027-04. Epoch AI estimate.Meta Temple — Temple, Texas. Owner Meta; users Meta. 178 MW online now. Epoch AI estimate.Google Red Oak — Red Oak, Texas. Owner Google; users unknown. 77 MW online now, 154 MW planned by 2026-12. Epoch AI estimate.Vantage TX1 — San Antonio, Texas. Owner unknown; users unknown. 32 MW online now, 128 MW planned by 2027-08. Epoch AI estimate.Google Midlothian — Midlothian, Texas. Owner Google; users unknown. 103 MW online now. Epoch AI estimate.Microsoft SAT40 — San Antonio, Texas. Owner Microsoft; users unknown. 75 MW online now. Epoch AI estimate.Microsoft SAT14 — San Antonio, Texas. Owner Microsoft; users unknown. 47 MW online now. Epoch AI estimate.Abilene 2.9 GWClaude 1.0 GWMilam County 857 MWAfton 528 MWDenton 282 MWSan Antonio 250 MWColorado City 207 MWTemple 178 MW
Circle area = planned IT power. Locations approximate.

fully online partly online (solid area = share running today) under construction

The sites

Data centerLocationOwnerMain usersOnline now (MW)Planned (MW)Full power by
OpenAI Stargate ShackelfordAbileneOracleOpenAI01,4002028-11
Buildings 1-5 shells complete and fully roofed. Next (2027-08): Building 1 is operational (estimate).
GoodnightClaudeGoogleGoogle DeepMind01,0062027-10
Progress is made on all buildings, Building 1 and 2 specically have begun to install cooling structures. Next (2027-03): Building 1 operational.
OpenAI Stargate MilamMilam CountySoftbankOpenAI08572028-12
Steel framing and roofing is underway for Building 1. Next (2028-12): All buildings finished, site is fully operational.
OpenAI Stargate AbileneAbileneOracleOpenAI824824online
Buildings 7-8 are estimated to be operational.
Crusoe Abilene ExpansionAbileneMicrosoftMicrosoft06722027-11
Land clearing continues. Next (2027-09): Building 1 operational.
Coreweave HeliosAftonCoreWeaveOpenAI1325282029-01
Building 1 operational at full capacity. Next (2028-01): Building 2 and 3 are operational at full capacity.
CoreWeave Denton TXDentonCoreWeaveOpenAI2622822027-05
Building 8 interior fit-out scheduled to begin. Next (2027-05): Building 8 projected operational.
Anthropic Barber LakeColorado CityCipher MiningAnthropic02072027-04
Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Next (2026-12): Building 1 Phase I is operational: 168 MW critical IT power (244 MW gross), running Google TPU v7 (chip type inferred, tagged likely).
Meta TempleTempleMetaMeta178178online
Building 3 is operational.
Google Red OakRed OakGoogle–771542026-12
Building 1 appears active - the surrounding land is finished including the site entrance and the parking lot. Next (2026-12): Building 2 is estimated to be operational.
Vantage TX1San Antonio––321282027-08
Building 1 operational; Roads around Building 1 complete, all cooling and side generator equipment construction has since finished as well. Next (2027-08): Estimated construction completion date of Building 2.
Google MidlothianMidlothianGoogle–103103online
Estimated full completion of the expanded row of cooling towers and backup generators for Building 1.
Microsoft SAT40San AntonioMicrosoft–7575online
Site has already been completed, with no more visible construction on any building.
Microsoft SAT14San AntonioMicrosoft–4747online
Building 2 fully operational, Building 1 expanded.

Grey rows: Epoch's latest construction note for each site, from satellite images, permits and filings.

Source: Epoch AI, ‘AI data centers’, licensed under CC BY 4.0; adapted by us (see Source and license below). Retrieved 2026-11-27.Estimates; locations approximate

Power coming online in Texas

By the end of 2027 the tracked Texas sites should reach about 4.23 GW of IT power. Hollow bars are planned dates.

0 GW2 GW4 GW6 GW202320242025202620272028End 2023: 0.00 GW IT powerEnd 2024: 0.07 GW IT powerEnd 2025: 0.60 GW IT powerToday: 1.73 GW IT powerEnd 2027: 4.23 GW IT powerEnd 2028: 6.33 GW IT power

online planned completion dates

Who builds and who uses them

Owners (by planned power): Oracle (2.2 GW), Google (1.3 GW), Softbank (857 MW), CoreWeave (810 MW), Microsoft (794 MW), Cipher Mining (207 MW).
AI companies running on these sites: OpenAI, Meta, Anthropic, Microsoft, Google DeepMind.

Local opposition and moratoria in Texas

WhereActionStatusDateWhat it doesSources
State of Texas (governor's directives)otherin force2026-08-03Gov. Abbott froze new data center projects pending a state audit, and the grid operator ERCOT paused part of its review of large new loads. In September he also told the state environmental agency, TCEQ, to stop issuing new permits for data centers. No end date has been set.The Texas Tribune The Texas Tribune
San Marcoszoning banin force2026-06-16The City Council voted 4-3 to make data centers ineligible in every zoning district, using its home-rule zoning powers. It became the first Texas city to do so. A state senator has said he will challenge the ban.The Texas Tribune
Hill Countymoratoriumlifted2026-05This appears to have been the first Texas county moratorium on data centers, a pause of up to one year. About two weeks later, after a developer sued for $100 million, commissioners unanimously rescinded it and adopted a checklist of developer requirements instead.The Texas Tribune
Hood Countymoratoriumfailed2026-02Commissioners twice considered a data center moratorium and did not pass it, after a state lawmaker warned that Texas counties lack the authority to impose one.The Texas Tribune

Full list: data center moratorium tracker.

See all states on the US AI data center map.

Source and license

This page is built on free public data from Epoch AI, a nonprofit research institute that tracks AI compute, chips and data centers. Epoch AI publishes its data under the Creative Commons Attribution 4.0 license (CC BY 4.0), which allows reuse with credit.

What we changed: we kept the US sites only; placed each site on the map from its street address (US Census geocoder), ZIP code centre or the town named in Epoch's sources, so positions are approximate; removed confidence tags from owner and user names; took planned power and dates from Epoch's construction timelines; and summed totals by state and company. State outlines: US Census Bureau (public domain), via the us-atlas project (ISC license).

Reuse: you may reuse this page’s charts, maps, tables, text and calculations, including for commercial use, under the CC BY 4.0 license. Credit both sources, for example: “Source: Superintelligence Index (thesuperintelligenceindex.com), based on Epoch AI data, CC BY 4.0”, and link to this page. Epoch AI’s underlying data stays under its own CC BY 4.0 license. Our terms of use do not restrict either.

Epoch AI provides its data as-is and without warranties; see sections 5 and 6 of the license (disclaimer of warranties and limitation of liability). Epoch AI is not affiliated with this site and does not endorse it or our calculations. Any errors in the adaptation are ours. Information only, not financial advice.

Map outline license (us-atlas)

State outlines are drawn from us-atlas v3 (states-10m), derived from US Census Bureau cartographic boundary files (public domain).

Copyright 2013-2019 Michael Bostock. Permission to use, copy, modify, and/or distribute this software for any purpose with or without fee is hereby granted, provided that the above copyright notice and this permission notice appear in all copies. THE SOFTWARE IS PROVIDED “AS IS” AND THE AUTHOR DISCLAIMS ALL WARRANTIES WITH REGARD TO THIS SOFTWARE INCLUDING ALL IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS. IN NO EVENT SHALL THE AUTHOR BE LIABLE FOR ANY SPECIAL, DIRECT, INDIRECT, OR CONSEQUENTIAL DAMAGES OR ANY DAMAGES WHATSOEVER RESULTING FROM LOSS OF USE, DATA OR PROFITS, WHETHER IN AN ACTION OF CONTRACT, NEGLIGENCE OR OTHER TORTIOUS ACTION, ARISING OUT OF OR IN CONNECTION WITH THE USE OR PERFORMANCE OF THIS SOFTWARE.

Frequently asked questions

How many AI data centers are in Texas?
Epoch AI tracks 14 large AI data centers in Texas. Smaller and older data centers are not in the list.
What is the largest AI data center in Texas?
OpenAI Stargate Shackelford in Abilene, owned by Oracle, planned at 1.4 GW of IT power by Epoch's estimate.
How much power do AI data centers in Texas use?
About 1.7 GW of IT power today across the tracked sites, rising to 6.5 GW when all are built.
Which companies are building AI data centers in Texas?
By planned power: Oracle, Google, Softbank, CoreWeave, Microsoft.
Are there data center moratoriums in Texas?
Our tracker lists 4 local or state action(s) in Texas; see the table on this page, each with sources.