AI data centers in Virginia
7 large AI data centers in Virginia are tracked by Epoch AI, in Sandston, Bristow, Sterling, Chester…. Together they are planned to draw 1.4 GW of IT power, 4% of all tracked US AI capacity (rank 9 of 18 states with a page).
- 7 sites
- 1.0 GW online today
- 1.4 GW planned
- #9 US state by planned power
fully online partly online (solid area = share running today) under construction
The sites
| Data center | Location | Owner | Main users | Online now (MW) | Planned (MW) | Full power by |
|---|---|---|---|---|---|---|
| STACK Infrastructure NVA02 | Manassas | – | – | 85 | 348 | 2028-01 |
| All buildings have begun construction (with groundwork starting for AI building 6), as depicted by satellite imagery. Next (2028-01): Estimate: All 6 AI data center buildings will be finished in 2028, assuming a groundbreak-to-operational timeline of 18-24 months. | ||||||
| QTS Richmond 3 | Sandston | – | – | 144 | 240 | 2027-02 |
| Building 2 and 3 are operational, based on the previous entry. Next (2027-02): Building 4 and 5 are operational, based on Building 5 being roughly 1 year behind Building 1 in satellite imagery. | ||||||
| QTS Richmond 1 | Sandston | – | – | 238 | 238 | online |
| No changes to the site since December 2025. | ||||||
| Google Bristow | Bristow | Google DeepMind | 238 | 238 | online | |
| Building 3 is operational, based off of colored motion artifacts from cooling towers. | ||||||
| QTS Richmond 2 | Sandston | – | – | 180 | 180 | online |
| Building 5 is estimated to be operational, based on the previous entry. | ||||||
| CoreWeave Chester VA | Chester | CoreWeave | OpenAI | 82 | 113 | 2027-06 |
| Based on satellite imagery, Building 3 has cleared its land and is beginning construction. Next (2027-06): Buildings 3 is estimated complete by the end of Q1 2027, based on the current PowerHouse schedule. | ||||||
| Google Arcola | Sterling | – | 77 | 77 | online | |
| Building 1 is operational, based off of colored motion artifacts from cooling towers and direct visual verification. | ||||||
Grey rows: Epoch's latest construction note for each site, from satellite images, permits and filings.
Power coming online in Virginia
By the end of 2027 the tracked Virginia sites should reach about 1.17 GW of IT power. Hollow bars are planned dates.
online planned completion dates
Who builds and who uses them
Owners (by planned power): Unknown (1.0 GW), Google (315 MW), CoreWeave (113 MW).
AI companies running on these sites: Google DeepMind, OpenAI.
Local opposition and moratoria in Virginia
| Where | Action | Status | Date | What it does | Sources |
|---|---|---|---|---|---|
| Loudoun County | pause | in force | 2026-11-17 | The Board of Supervisors voted 7-1 to pause new legislative applications for data centers and substations. Reasons cited were grid capacity, infrastructure, noise and air quality. Reports give the length as 10 months; the county describes it as up to 12 months. | FOX 5 DC |
| Prince William County (PW Digital Gateway) | other | in force | 2025-08-07 | A circuit judge voided the county's rezoning for the large Digital Gateway data center corridor because hearing notices were improper. The ruling was upheld on appeal, and in July 2026 the developer QTS dropped its appeal, so those approvals no longer stand. | Potomac Local FOX 5 DC |
Full list: data center moratorium tracker.
See all states on the US AI data center map.
Source and license
This page is built on free public data from Epoch AI, a nonprofit research institute that tracks AI compute, chips and data centers. Epoch AI publishes its data under the Creative Commons Attribution 4.0 license (CC BY 4.0), which allows reuse with credit.
- Epoch AI, ‘AI data centers’. Published online at epoch.ai. Retrieved from ‘https://epoch.ai/data/ai-data-centers’ [online resource]. Retrieved 2026-11-27.
What we changed: we kept the US sites only; placed each site on the map from its street address (US Census geocoder), ZIP code centre or the town named in Epoch's sources, so positions are approximate; removed confidence tags from owner and user names; took planned power and dates from Epoch's construction timelines; and summed totals by state and company. State outlines: US Census Bureau (public domain), via the us-atlas project (ISC license).
Reuse: you may reuse this page’s charts, maps, tables, text and calculations, including for commercial use, under the CC BY 4.0 license. Credit both sources, for example: “Source: Superintelligence Index (thesuperintelligenceindex.com), based on Epoch AI data, CC BY 4.0”, and link to this page. Epoch AI’s underlying data stays under its own CC BY 4.0 license. Our terms of use do not restrict either.
Epoch AI provides its data as-is and without warranties; see sections 5 and 6 of the license (disclaimer of warranties and limitation of liability). Epoch AI is not affiliated with this site and does not endorse it or our calculations. Any errors in the adaptation are ours. Information only, not financial advice.
Map outline license (us-atlas)
State outlines are drawn from us-atlas v3 (states-10m), derived from US Census Bureau cartographic boundary files (public domain).
Copyright 2013-2019 Michael Bostock. Permission to use, copy, modify, and/or distribute this software for any purpose with or without fee is hereby granted, provided that the above copyright notice and this permission notice appear in all copies. THE SOFTWARE IS PROVIDED “AS IS” AND THE AUTHOR DISCLAIMS ALL WARRANTIES WITH REGARD TO THIS SOFTWARE INCLUDING ALL IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS. IN NO EVENT SHALL THE AUTHOR BE LIABLE FOR ANY SPECIAL, DIRECT, INDIRECT, OR CONSEQUENTIAL DAMAGES OR ANY DAMAGES WHATSOEVER RESULTING FROM LOSS OF USE, DATA OR PROFITS, WHETHER IN AN ACTION OF CONTRACT, NEGLIGENCE OR OTHER TORTIOUS ACTION, ARISING OUT OF OR IN CONNECTION WITH THE USE OR PERFORMANCE OF THIS SOFTWARE.
Frequently asked questions
- How many AI data centers are in Virginia?
- Epoch AI tracks 7 large AI data centers in Virginia. Smaller and older data centers are not in the list.
- What is the largest AI data center in Virginia?
- STACK Infrastructure NVA02 in Manassas, owned by an undisclosed owner, planned at 348 MW of IT power by Epoch's estimate.
- How much power do AI data centers in Virginia use?
- About 1.0 GW of IT power today across the tracked sites, rising to 1.4 GW when all are built.
- Which companies are building AI data centers in Virginia?
- By planned power: Unknown, Google, CoreWeave.
- Are there data center moratoriums in Virginia?
- Our tracker lists 2 local or state action(s) in Virginia; see the table on this page, each with sources.